Numeracy Intermediate June 2024 Unit 2 Q5

WJECIntermediateCurrent spec11 marksFractionsPercentagesVolume & Surface Area

5. The Severn Bridge was built in 1966 to allow vehicles to travel between England and Wales.

The bridge has a width of 23 m and a total length of 1600 m.
The section of the bridge between the two towers is 988 m long.

The tarmac road surface is 0.035 m thick.

The cables from the towers to support the road are made from 18 000 miles of wire.

(a)

What fraction of the total length of the bridge is the section between the two towers?
Give your fraction in its simplest form. [2]

(b)

Calculate the length of the wire used to make the cables in kilometres. [2]

(c)

The cost of tarmac is £250 per m\(^{3}\).

Calculate the cost of the volume of tarmac needed to resurface the total length of the Severn Bridge. [3]

(d)

Some of the tolls charged for a car to enter Wales are given in the table below.

Year2004200920142019
Toll for a car£4.60£5.40£6.40FREE

In which of the following 5-year periods was there the greatest percentage increase in the toll?

2004 to 20092009 to 20142014 to 2019

State the percentage increase for this 5-year period.
You must show all your working. [4]

The greatest percentage increase in the toll was in the period …………… to …………… .

The percentage increase was ……………