D1 June 2014 (R) Q6

EdexcelOld spec7 marksCritical Path Analysis

6.

(i) Draw the activity network described in the precedence table below, using activity on arc and the minimum number of dummies.
ActivityImmediately preceding activities
A–
B–
C–
DA, C
EB
FE
GA
HD, F
ID, F
JH, I
(ii) Explain why each of your dummies is necessary.