A2 June 2023 Q2

EdexcelCurrent spec7 marksCritical Path Analysis

2.

Figure 3: activity network: A(3) and C(4) and D(7) leave the start; B(5) follows A; C ends at the same event as B; a dummy runs from the end of D to the end of B and C; E(1) and F(2) leave that event; H(1) follows E; G(4) follows D; F, G and H end at the finish
Figure 3

The network in Figure 3 shows the activities that need to be undertaken to complete a project. Each activity is represented by an arc and the duration, in hours, of the corresponding activity is shown in brackets.

(a)
(i) Complete Diagram 1 in the answer book to show the early event times and the late event times.
(ii) State the minimum completion time of the project. (3)
Diagram 1: the network of Figure 3 with an empty box at each event for the early event time (top) and late event time (bottom)
Diagram 1

The table below lists the number of workers required for each activity in the project.

ActivityNumber of workers
A2
B1
C2
D2
E3
F2
G1
H3

Each worker is able to do any of the activities. Once an activity is started it must be completed without interruption. It is given that each activity begins at its earliest possible start time.

(b)
(i) On Grid 1 in the answer book, draw a resource histogram to show the number of workers required at each time.
(ii) Hence state the time interval(s) when six workers are required. (4)
Grid 1: blank grid, number of workers from 0 to 8 against time in hours from 0 to 14
Grid 1