D1 June 2014 Q2

EdexcelOld spec7 marksCritical Path Analysis

2.

(a) Draw the activity network described in the precedence table below, using activity on arc and exactly two dummies. (5)
ActivityImmediately preceding activities
A–
B–
C–
DA, B
EC
FA, B
GA, B
HE, F
ID
JD, G
KH
(b) Explain why each of the two dummies is necessary. (2)