D1 June 2006 Q5
5.

An engineering project is modelled by the activity network shown in Figure 4. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. Each activity requires one worker. The project is to be completed in the shortest time.
The chief engineer visits the project on day 15 and day 25 to check the progress of the work.
Given that the project is on schedule,
| Scheme | Marks |
|---|---|
![]() | M1 A1 (2) M1 A1 (2) |
| (4) |
Notes
M1 All top boxes completed → increasing generally
A1 c.a.o.
M1 All lower boxes completed ← decreasing generally
A1 c.a.o.
| Scheme | Marks |
|---|---|
| \(A - C - G - I - M\) \(\phantom{A - C -{}} H - K\) | A1 |
| (1) |
Notes
A1 c.a.o. all 7 listed – no extras
| Scheme | Marks |
|---|---|
| Float on \(D = 21 - 5 - 14 = 2\) | B1ft |
| Float on \(F = 42 - 20 - 14 = 8\) | M1 A1ft |
| (3) |
Notes
B1ft cao ft from diagram
M1 method correct or ft correct answer (top ≤ bottom at both ends; must see appropriate working for M1)
A1ft cao ft from diagram
| Scheme | Marks |
|---|---|
![]() | M1 A1 A1ft A1 |
| (4) |
Notes
M1 At least one of their critical paths + 3 non-critical stated including floats (must be complete answer)
A1 critical activities correct
A1ft 4 non-critical activities correct ft from diagram; must include a float per activity
A1 cao – on non critical
| Scheme | Marks |
|---|---|
| Day 15: \(C\) | B1 |
| Day 25: \(G, H, E, F\) | B2,1,0 |
| (3) | |
| (15 marks) |
Notes
B1 cao
B2 cao
B1 if one extra or one omission

