D1 January 2013 Q7
7.

Figure 7 is the activity network relating to a building project. The activities are represented by the arcs. The number in brackets on each arc gives the time to complete the activity. Each activity requires one worker.
The project must be completed in the shortest possible time.
| Scheme | Marks |
|---|---|
| Activity K depends on activities E, F and B, but activity I depends on F and B only. | B2, 1, 0 |
| (2) |
Notes
a1B1 K, I, E and at least one of B or F referred to. Correct statement but may be incomplete give bod here.
a2B1 Clear correct statement no bod (at least one of only B or F referred to can score this mark).
| Scheme | Marks |
|---|---|
![]() | M1 A1 M1 A1 |
| (4) |
Notes
b1M1 All top boxes complete, values generally increasing left to right, condone one ‘rogue’ (if values do not increase from left to right then if one value is ignored and then the values do increase from left to right then this is considered to be only one rogue value).
b2A1 CAO
b2M1 All bottom boxes complete, values generally decreasing right to left, condone one rogue. Condone missing 0 or 21 for the M only.
b2A1 CAO
| Scheme | Marks |
|---|---|
| Critical activities are: A, F, I, L | B1 |
| (1) |
Notes
c1B1 CAO
| Scheme | Marks |
|---|---|
| Total float on G = 15 – 6 – 6 = 3 | M1 A1 |
| (2) |
Notes
d1M1 Correct calculation seen, all three numbers correct (ft), float \(\geqslant 0\)
d1A1 CAO (no ft on this mark)
| Scheme | Marks |
|---|---|
![]() | M1 A1 A1 A1 |
| (4) |
Notes
e1M1 At least 9 activities including at least 5 floats. Scheduling diagram scores M0.
e1A1 The correct critical activities dealt with correctly
e2A1 All correct non-critical activities present with floats with 5 non-critical activities correct
e3A1 All 9 non-critical activities correct
| Scheme | Marks |
|---|---|
| Activities A, C and D must be happening at time 5.5 | B1 |
| (1) |
Notes
f1B1 CAO
| Scheme | Marks |
|---|---|
| E.g. Activities F, B, C and G together with \(9 \lt \text{time} \lt 10\) stated | M1 |
| So 4 workers are needed | A1 |
| (2) | |
| (16 marks) |
Notes
g1M1 A statement with the correct number of workers and details of either time or activities correct. If no part of their statement is correct then allow M mark (only) on the ft with time and activities from their 13 activity, 9 float diagram. Scheduling the activities only or a lower bound calculation argument scores M0.
g1A1 A correct, complete full statement details of time and activities (The two options are F, B, C and G with \(9 \lt \text{time} \lt 10\) or F, C, G and H with \(10 \lt \text{time} \lt 11\)). Please note strict inequalities for the time. Allow e.g. on ‘day 10’ as equivalent to \(9 \lt \text{time} \lt 10\).

