D1 January 2009 Q3

EdexcelOld spec7 marksCritical Path Analysis

3.

(a) Draw the activity network described in this precedence table, using activity on arc and exactly two dummies. (5)
ActivityImmediately preceding activities
A-
B-
C-
DB
EB,  C
FB, C
GF
HF
IG, H
JI
(b) Explain why each of the two dummies is necessary. (2)