D1 June 2014 (R) Q7
7.

A project is modelled by the activity network shown in Figure 5. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. Each activity requires one worker. The project is to be completed in the shortest possible time.
The project is to be completed in the minimum time using as few workers as possible.

| Scheme | Marks |
|---|---|
| M1 A1 | |
| M1 A1 | |
| (4) |
Notes
a1M1: All top boxes complete, values generally increasing left to right, condone one rogue.
a1A1: CAO
a2M1: All bottom boxes complete, values generally decreasing right to left, condone one rogue. Condone missing 0 or 22 for the M only.
a2A1: CAO
| Scheme | Marks |
|---|---|
| Total float for D = 12 – 4 – 4 = 4 | M1 A1 |
| (2) |
Notes
b1M1: Correct calculation for their activity D seen – their three numbers correct. Final value must be non-negative.
b1A1: CAO – no ft on this mark. The answer of 4 (with no working) scores no marks.
| Scheme | Marks |
|---|---|
| \(\dfrac{52}{22} \approx 2.36\) so 3 workers | M1 A1 |
| (2) |
Notes
c1M1: Attempt to find lower bound: [42-62 / their finish time].
c1A1: CAO – correct calculation seen then 3. No working scores M0 A0.
e.g.

| Scheme | Marks |
|---|---|
| M1 | |
| A1 | |
| A1 | |
| (3) | |
| (11 marks) |
Notes
d1M1: Not a cascade chart. 3 ‘workers’ used at most and at least 7 activities placed.
d2A1: 3 workers. All 11 activities present (just once). Condone one error either precedence, time interval or activity length.
d3A1: 3 workers. All 11 activities present (just once). No errors.
For reference:
| Activity | Duration | Time interval | IPA |
|---|---|---|---|
| A | 4 | 0 – 7 | - |
| B | 5 | 0 – 5 | - |
| C | 3 | 0 – 5 | - |
| D | 4 | 4 – 12 | A |
| E | 2 | 4 – 9 | A |
| F | 3 | 5 – 9 | B |
| G | 4 | 5 – 9 | B, C |
| H | 6 | 9 – 15 | E, F, G |
| I | 4 | 9 – 15 | G |
| J | 10 | 9 – 22 | D, E, F |
| K | 7 | 15 – 22 | H, I |