D1 June 2019 Q7

EdexcelOld spec14 marksCritical Path Analysis

7.

Figure 5: activity network for activities A to M with early and late event times at each node
Figure 5

The network in Figure 5 shows the activities that need to be undertaken in order to complete a project. Each activity is represented by an arc. The number in brackets is the duration of the activity in hours. The early event times and late event times are shown at each node. The project can be completed in 23 hours.

Given that the total float on activity G is 1 hour,

(a) find the values of \(w\), \(x\), \(y\) and \(z\). (4)
(b) Explain the purpose of the dummy activity that has a late event time of 16 (1)
(c) List the critical activities. (1)

This project is being completed by a company that has only two permanent workers available. The project must be completed in 23 hours and, in order to achieve this, the company is prepared to hire additional workers at a cost of £35 per hour payable only for the time that the workers are engaged in activities. The company wishes to minimise the money spent on additional workers. Any worker can undertake any activity and each activity requires only one worker. Once an activity has been started it must be completed without interruption and by the same worker.

(d) Explain why the company cannot complete the project in 23 hours using only their permanent workers. (1)
(e) Schedule the activities to workers on Grid 1 in the answer book so that the project is completed in 23 hours using the minimum number of workers and at minimum cost to the company. (3)
(f) Calculate the minimum extra cost to the company. You must make your working clear. (2)

Due to bad weather, activity H may take 7 hours to complete.

(g) Explain what affect this would have on the minimum time taken to complete the whole project. (You do not need to reschedule the project.) (2)