A2 October 2021 Q2

EdexcelCurrent spec9 marksCritical Path Analysis

2.

Figure 2: activity network: A(4), B(6) and C(10) leave the start; D(2) and E(4) follow A; B and E end at the same event, from which a dummy runs up to the end of D, and H(7), I(2) and F(5) leave; G(6) follows the end of D and the dummy; C and F end at the same event, from which a dummy runs to the end of I, and L(7) and M(5) leave; J(7) follows G and H; K(6) follows the end of I and the dummy; J, K and L end at the finish; a dummy runs from the end of M to the finish
Figure 2

A project is modelled by the activity network shown in Figure 2. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, to complete the corresponding activity.

(a) Complete Diagram 1 in the answer book to show the early event times and the late event times. (4)
Diagram 1: the network of Figure 2 with an empty box at each event for the early event time (top) and late event time (bottom)
Diagram 1

Each activity requires one worker and the project must be completed in the shortest possible time using as few workers as possible.

(b) Calculate a lower bound for the number of workers needed to complete the project in the shortest possible time. You must show your working. (2)
(c) Schedule the activities using Grid 1 in the answer book. (3)
Grid 1: blank scheduling grid with time from 0 to 26
Grid 1