AS June 2025 Q2

EdexcelAS paperCurrent spec8 marksCritical Path Analysis

2.

ActivityImmediately preceding activities
A-
B-
C-
DB
EA, B
FB
GB
HC, D
IG, H
JE
KE, F, I
LG, H
MG, H
(a) Explain how you can deduce from the precedence table that at least one dummy will be needed when drawing the activity network. Your explanation should refer to specific activities. (1)
(b) Draw the activity network described in the precedence table, using activity on arc. Your activity network must contain the minimum number of dummies only. (5)

Each activity in the precedence table takes 3 hours to complete.

(c) State the minimum completion time. (1)

One of the activities now needs to be chosen to be extended by an hour. When the change is made the minimum completion time must not be affected.

(d) List the activities that could be chosen. (1)