A2 June 2025 Q6

EdexcelCurrent spec13 marksCritical Path Analysis

6.

Figure 3: activity network with activities A(2), B(4), C(3), D(7), E(4), F(5), G(5), H(6), I(10), J(2), K(6), L(10), M(7) and three dummies
Figure 3

A project is modelled by the activity network shown in Figure 3. The activities are represented by the arcs. The number in brackets on each arc gives the time, in hours, to complete the corresponding activity. The project is to be completed in the shortest possible time.

(a) Complete Table 1 in the answer book to show the immediately preceding activities for each activity. (2)
ActivityImmediately preceding activitiesActivityImmediately preceding activities
AG
BH
CI
DJ
EK
FL
M

Table 1

(b) Complete Diagram 1 in the answer book to show the early event times and the late event times. (4)
Diagram 1: the network of Figure 3 with an empty box at each event for the early event time (top) and late event time (bottom)
Diagram 1
(c) Draw a Gantt chart for this project on Grid 1 in the answer book. (4)
Grid 1: blank grid with a time axis from 0 to 24
Grid 1
Figure 4: resource histogram, number of workers against time in hours: 4 from 0 to 2, 5 from 2 to 3, 8 from 3 to 4, 6 from 4 to 7, 8 from 7 to 8, 9 from 8 to 9, 7 from 9 to 12, 6 from 12 to 13, 5 from 13 to 15, 4 from 15 to 17, 2 from 17 to 20
Figure 4

The resource histogram in Figure 4 shows the number of workers required when each activity starts at its earliest possible time. When an activity is started it must be completed without interruption. Each activity requires at least one worker.

(d) By considering which activities are happening each hour, and by working backwards from the minimum project completion time, complete Table 2 in the answer book to show the number of workers needed for each activity. (3)
ActivityNumber of WorkersActivityNumber of Workers
AG
BH
CI
DJ
EK
FL
M

Table 2