D1 June 2011 Q7

EdexcelOld spec16 marksCritical Path Analysis

7.

Figure 7: activity network on events 1 to 8: A (4) 1–2, B (7) 1–3, dummy 3–2, E (2) 2–5, C (4) 2–4, D (5) 3–4, F (5) 3–6, G (4) 3–7, dummy 4–5, H (4) 4–6, I (3) 5–6, J (10) 5–8, K (5) 6–8, dummy 6–7, L (6) 7–8
Figure 7

A project is modelled by the activity network shown in Figure 7. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. Each activity requires one worker. The project is to be completed in the shortest possible time.

(a) Complete the precedence table in the answer book. (3)
(b) Complete Diagram 1 in the answer book, to show the early event times and late event times. (4)
(c) State the critical activities. (2)
(d) On the grid in your answer book, draw a cascade (Gantt) chart for this project. (4)
(e) By considering the activities that must take place between time 7 and time 16, explain why it is not possible to complete this project with just 3 workers in the minimum time. (3)