D1 June 2010 Q8
8.

A project is modelled by the activity network shown in Figure 7. The activities are represented by the arcs. The number in brackets on each arc gives the time, in days, to complete the activity. Each activity requires one worker. The project is to be completed in the shortest possible time.
You must justify your answer. (2)
| Scheme | Marks |
|---|---|
![]() | M1 A1 M1 A1 |
| (4) |
Notes
1M1: Top boxes completed generally increasing left to right.
1A1: CAO.
2M1: Bottom boxes completed generally decreasing right to left.
2A1: CAO.
| Scheme | Marks |
|---|---|
| Critical activities: C E H J L | B1 |
| (1) |
Notes
1B1: Critical activities cao.
| Scheme | Marks |
|---|---|
![]() | M1 A1 A1 A1 |
| (4) |
Notes
1M1: At least 10 activities placed, at least five floats. Scheduling diagram gets M0.
1A1: my critical activities correct.
2A1: condone one error on my non-critical activities.
3A1: my non-critical activities correct.
| Scheme | Marks |
|---|---|
| 4 workers needed e.g. at time 8 ½ (noon on day 9) activities E, D, F and G must be happening. | B2, 1, 0 |
| (2) | |
| (11 marks) |
Notes
1B1: A correct statement, details of either time (7<time<9, 8<day<10), or activities, bod gets B1. Allow 1 B mark (only) on ft from their 12 activity, 7 float diagram.
2B1: A correct, complete full statement details of time and activities.