A2 October 2021 Q7
7.

Figure 5 shows a partially completed activity network for a project that consists of 14 activities.
| Activity | Immediately preceding activities | Activity | Immediately preceding activities |
|---|---|---|---|
| A | E | ||
| B | F | ||
| C | G | ||
| D | H |
The precedence table for the remaining 6 activities is given below.
| Activity | Immediately preceding activities |
|---|---|
| I | D, E, G, H |
| J | D, E, G, H |
| K | E, G, H |
| L | I, J, K |
| M | J, K |
| N | J, K |
[The activity network in the answer book is a copy of Figure 5.]
Given that all 14 activities have the same duration,
| Scheme | Marks | AO | ||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| B1 B1 | 1.1b 1.1b | ||||||||||||||||||
| (2) |
Notes
(a) B1: Either row G or H correct
B1: All rows correct (condone blanks in A, B and C rows)
| Scheme | Marks | AO |
|---|---|---|
e.g.![]() | M1 A1 A1 A1 | 2.1 1.1b 1.1b 1.1b |
| (4) |
Notes
Condone lack of, or incorrect, numbered events throughout. ‘Dealt with correctly’ means that the activity starts from the correct event but need not necessarily finishes at the correct event, e.g. ‘K dealt with correctly’ requires the correct precedences for this activity, i.e. E, G and H labelled correctly and leading into the same node and K starting from that node but do not consider the end event for K. Activity on node is M0
Assume that a solid line is an activity which has not been labelled rather than a dummy (even if in the correct place for where a dummy should be)
Ignore incorrect or lack of arrows on the activities for the first three marks only
(b) M1: At least five activities (labelled on arc), at least two dummies placed
A1: Activities I, J, K and first dummy + arrow dealt with correctly
A1: Activities L, M, N and a second dummy + arrows dealt with correctly
A1: cso – all arrows present for every activity with one finish and exactly three dummies. Note that this is not a unique solution e.g. M and N could be interchanged so please check these carefully. Please check all arcs carefully for arrows – if there are no arrows on any dummies then M1 only
Note that additional (but unnecessary) ‘correct’ dummies that still maintain precedence for the network should only be penalised with the final A mark if earned
| Scheme | Marks | AO |
|---|---|---|
| If all activities have the same duration then any critical path must contain 5 activities. All paths that pass-through D have only 4 activities and so therefore D cannot be critical. | B1 B1 | 2.4 2.4 |
| (2) | ||
| (8 marks) |
Notes
(c) B1: Explains that all critical paths must contain 5 activities (oe method e.g., attempting a forward and backward pass with each activity having the same duration)
B1: cao that D cannot be critical with mention of all paths through D only contain 4 activities (oe method e.g., showing that the total float on activity D is not zero)
SCB1: stating or implying that D has a float of 1 (oe) by considering a forward pass (which may or may not be done mathematically) up to at least activity D
