EdexcelCurrent spec8 marksCritical Path Analysis

7.

Figure 5: partial activity network: A, B and C leave the start; D, E and F leave the end of A; F ends at the end of B; a dummy runs from there to the end of C; G leaves the end of B and F; H leaves the end of C and the dummy; E, G and H end at the same event; D ends at its own event
Figure 5

Figure 5 shows a partially completed activity network for a project that consists of 14 activities.

(a) Complete the precedence table in the answer book for the 8 activities in Figure 5. (2)
ActivityImmediately preceding activitiesActivityImmediately preceding activities
A E 
B F 
C G 
D H 

The precedence table for the remaining 6 activities is given below.

ActivityImmediately preceding activities
ID, E, G, H
JD, E, G, H
KE, G, H
LI, J, K
MJ, K
NJ, K
(b) Complete the activity network in the answer book for the project. Your completed activity network must contain only the minimum number of dummies. (4)

[The activity network in the answer book is a copy of Figure 5.]

Given that all 14 activities have the same duration,

(c) explain why activity D cannot be critical. (2)