D2 June 2014 (R) Q6

EdexcelOld spec7 marksAllocation

6. Four workers, A, B, C and D, are to be assigned to four tasks, 1, 2, 3 and 4. Each worker must be assigned to just one task and each task must be done by just one worker.

Worker C cannot do task 4 and worker D cannot do task 1.

The cost of assigning each worker to each task is shown in the table below.

The total cost is to be minimised.

1234
A29153230
B34264032
C282735–
D–213331

Formulate the above situation as a linear programming problem. You must define your decision variables and make the objective function and constraints clear. (7)