Numeracy Higher November 2020 Unit 1 Q8

WJECHigherCurrent spec5 marksDirect & Inverse Proportion

8. On a building site, 4 bricklayers were able to lay 2000 bricks in 8 hours.

To complete the work on time, bricklayers will need to lay 9000 bricks in 10 hours.

(a) Calculate how many bricklayers would be needed to lay 9000 bricks in 10 hours.
You must show all your working. [4]
(b) Give one assumption that you made in answering part (a). [1]