D1 January 2008 Q7
7.

Phil sells boxed lunches to travellers at railway stations. Customers can select either the vegetarian box or the non-vegetarian box.
Phil decides to use graphical linear programming to help him optimise the numbers of each type of box he should produce each day.
Each day Phil produces \(x\) vegetarian boxes and \(y\) non-vegetarian boxes.
One of the constraints limiting the number of boxes is
\[x + y \geqslant 70.\]This, together with \(x \geqslant 0\), \(y \geqslant 0\) and a fourth constraint, has been represented in Figure 7. The rejected region has been shaded.
Two further constraints are:
\[x + 2y \leqslant 160\]\[\text{and} \quad y \gt 60.\]Phil makes a profit of £1.20 on each vegetarian box and £1.40 on each non-vegetarian box. He wishes to maximise his profit.
| Scheme | Marks |
|---|---|
| \(y \geqslant 2x\) | B2, 1, 0 |
| (2) |
Notes
Q7(a) 1B1 2 (or ½) one correct side, condone any inequality or equals, or bod
2B1 cao
| Scheme | Marks |
|---|---|
| \(x + 2y = 160\) correctly drawn \(y = 60\) correctly drawn and distinctive (strict inequality) Shading correct | B4, 3, 2, 1, 0 |
| (4) |
Notes
(b) 1B1–4B1 −1 e.e. Errors to look for: \(y = 60\) distinct in some way; lines correct to \(\leqslant\) 1 small square 1 at axis; Labels on lines; Ruler
| Scheme | Marks |
|---|---|
| R correct | B1ft |
| (1) |
Notes
(c) 1B1ft R ‘correct’, ft their lines, but shading needs to be correct
| Scheme | Marks |
|---|---|
| Profit line added or Point testing seen | M1 |
| correctly done | A1 |
| 70 boxes identified | A1 |
| (3) |
Notes
(d) 1M1 Attempt at profit line (axis to axis) or point testing 2 points
1A1 Profit line correct (within 1 sm square) or three points tested correctly
2A1 cao
| Scheme | Marks |
|---|---|
| \((P =)\ 1.2x + 1.4y\) | B1 |
| (1) |
Notes
(e) 1B1 cao
| Scheme | Marks |
|---|---|
| Profit line added or Point testing seen | M1 |
| correctly done | A1ft A1 |
| (32, 64) identified. | A1 |
| (4) |
Notes
(f) 1M1 Attempt at profit line (axis to axis) or point testing 2 points
1A1ft correct but ft their R and their (e) for profit line and 3 point testing
2A1 correct (so a mark for correct with no need to ft)
3A1 cao (32, 64) only
| Scheme | Marks |
|---|---|
| £128.00 | A1ft |
| (1) | |
| (16 marks) |
Notes
(g) 4A1 cao follow through (ignore units).